Open Heart
Gallery Operating theatre : Royal Brompton
This client required a state of the Art operating theatre with a light fitting costing just over £800,000.00. that contained media interface to transfer the images of an operation all over the world with commentary from the surgeons.
The ancilliary areas were developed around the operating theatre in the first instance whilst the theatre remained operational. No greater degree of attention to cleanliness can be deployed than working in an operating theatre environment. Demanding and rewarding when you achieve the levels of excellence in construction required and we did.
The Gallery dome of the Operating theatre was removed. The theatre over a 48 hour period totally refitted with new medical gases, vacuum, voice/data/image systems.
Project completed in a total of 4 weeks £450,000.00. A 24/7/365 project